Project Overview
A multifamily developer was closing out a project of more than 300 units with move-in dates committed to tenants. The kitchen fixture supplier chosen at the start of the build was not going to deliver on schedule. With occupancy dates and the penalties behind them on the line, the developer brought in Allora USA to supply the remaining fixtures from stock. Deliveries arrived in sequence with construction, every occupancy date held, and the developer has since made Allora USA a preferred supplier for its multifamily work.
|
|
|
|---|---|
|
Project |
Multifamily development, 300+ units, nearing completion |
|
Problem |
Original kitchen fixture supplier unable to meet delivery deadlines |
|
Stakes |
Tenant move-in commitments, with penalties and lost rent if missed |
|
Scope |
Kitchen fixtures for the remaining units |
|
Allora's role |
Late-stage replacement supplier: in-stock product, sequenced delivery, dedicated account manager |
|
Outcome |
All scheduled occupancy dates met; Allora named preferred supplier for future projects |
The Challenge
Late in a build, the fixture package is on the critical path. Kitchens can't close out without sinks and faucets, units can't pass final inspection without closed-out kitchens, and tenants can't move in without passed inspections. When the original supplier's delivery dates slipped, every one of those dominoes was in line to fall.
The developer had no slack to work with. A replacement supplier would need to meet four conditions at once:
- Stock on hand. No lead time for manufacturing; product had to ship from inventory.
- Quantity. Enough to cover the remaining units in one program, not a trickle.
- Sequenced delivery. Fixtures arriving in the order crews were installing them, so nothing sat on site and nothing held up a floor.
- A direct line. Someone who could answer a site question or adjust a shipment the same day.
The Solution
Allora USA supplied the remaining kitchen fixtures from its domestic inventory. Because the product was in stock, the first shipment went out without a manufacturing lead time. A dedicated account manager was assigned to the project and worked directly with the site team to match deliveries to the construction sequence and to handle changes as they came up.
|
Requirement |
How it was met |
|---|---|
|
Stock on hand |
Fixtures shipped from Allora's in-stock inventory, no production wait |
|
Quantity |
Full remaining scope supplied under one program |
|
Sequenced delivery |
Shipments scheduled against the install sequence so crews were never waiting |
|
A direct line |
One account manager, same-day response on site questions and adjustments |
The Result
Every scheduled occupancy date was met. Construction continued without a stop for fixtures, no tenant move-in was pushed, and the developer avoided the penalties and lost rent a slip would have carried.
The outcome that matters most came after. The developer selected Allora USA as a preferred supplier for its future multifamily projects, moving Allora from emergency replacement to first call.
The Takeaway
A fixture supplier failing late is rarely a surprise. The warning signs show up weeks earlier: slipping confirmations, partial shipments, a rep who stops returning calls. By the time it's a crisis, the only thing that saves the schedule is a supplier with the product already on a shelf in the same country.
Two things to do on the next project:
- Qualify a backup fixture supplier before you need one. Ask the question up front: if the primary slips 30 days at month ten, who ships from stock? Having the answer costs nothing. Finding it at month ten costs a schedule.
- Ask any supplier to show inventory, not promise it. "Available" and "in stock in our U.S. warehouse" are different sentences. On a time-critical project, only the second one counts.
Frequently Asked Questions
What are typical lead times for multifamily plumbing fixtures?
Made-to-order or imported fixtures commonly run 8 to 16 weeks, and longer when a factory is backed up. In-stock product from a domestic warehouse ships in days. The difference matters most late in a project, when there is no float left to absorb a factory delay.
What should a developer do when a fixture supplier is going to miss the delivery date?
Confirm the slip in writing, quantify the remaining scope by unit and floor, and get a stock check from an alternate supplier the same day. The question to ask is not "can you supply this" but "how many are on your shelf right now and when can the first truck leave." If the answer covers the install sequence, the schedule is recoverable.
How do you keep fixture deliveries matched to the construction sequence?
Ship in the order crews install, not all at once. On this project Allora's account manager scheduled shipments floor by floor against the site team's sequence, so product arrived as each area was ready and nothing sat on site or held up a trade.
Should a multifamily project qualify a backup fixture supplier?
Yes, during buyout. Ask any candidate what they hold in U.S. stock, in what quantities, and how fast they can ship a full floor. A supplier that can answer with numbers is a backup; one that answers with "available" is not.
Is your fixture supplier going to make the date?
If deliveries are slipping, send Allora USA your fixture schedule and remaining quantities. A project specialist will tell you what's in stock, what can ship, and how fast, so you know your options before the schedule decides for you. If you're still in planning, the same review qualifies Allora as your backup before you need one.
Or call a project specialist directly: (571) 291-3484, Monday to Friday, 8 AM to 4 PM ET.